LESSON 8
PRACTICE EXERCISE
The following items will test your knowledge of the material covered in this
lesson. There is only one correct answer for each item. When you complete
the exercise, check your answers with the answer key. If you answer any
items incorrectly, go back to the part of the lesson that contains the
information involved and study again.
1. The pipeline of the IPDS is configured in what length pipeline sets?
A. 5-mile.
B. 10-mile.
C. 19-foot.
D. 20-foot.
at?
A. 150 psi.
B. 200 psi.
C. 210 psi.
D. 350 psi.
3. The beach interface is an assembly of adapters used to connect the IPDS
to the.
A. PSE.
B. OPDS.
C. TPT.
D. AFFF.
4. How often does the water detector kit need to be tested when in operation
of dispensing assembly?
A. Every 2 hours.
B. Every 3 hours.
C. Every 4 hours.
D. Every 5 hours.
5. What is the first step in site and route selection?
A. Survey using topographic map.
B. Preliminary plot plan.
C. Roadway and berm construction.
D. Mark the pipeline trace.
12-82
QM 5099