Home
Download PDF
Order CD-ROM
Order in Print
Home
>
Quartermaster Documents and Training Manuals
>
> Control Class III and Pipeline Operations
Lesson 1 Theory of Flow
Part A- Static Fluid (Flow of Fuel in Pipelines)
Dynamic Pressure
Part C-Design Fuel
Figure 1-1, Kinematic viscosity - QM50990009
Part D- Dynamic Fluid Flow
Figure 1-1, Kinematic viscosity - QM50990011
Part E -Types of Flow
Figure 1-2. Friction Factor versus Reynold's number
Darcy Weisbach Equation
Darcy Weisbach Equation -Cont.
Lesson 1 Practice Exercise - QM50990017
Lesson 2 Line Fill and Friction Loss
Part A-Friction Loss
Figure 2-1. Head loss due to friction
Table 2-1. Friction head loss correction factors
Part C-Feet of Head Available
Part D-Friction Loss
Part E-Line Fill
Lesson 2 Practice Exercise - QM50990027
Lesson 2 Practice Exercise -Cont.
Lesson 3 Design
Part A-Hydraulic Gradient
Determine the Hydraulic Gradient
Figure 3-2. Operating characteristics of standard pipeline pumping stations
Figure 3-3. Design capacity of standard military, lightweight steel and aluminum pipe
Lesson 3 Practice Exercise - QM50990034
Lesson 4 Supervise the Selection and Prepare A Class III Supply Point
Part A-Preparation for Movement
Part C-Selection of Class III Supply Point
Site Selection - QM50990038
Figure 4-1. Site selection guidelines for a Class III supply point
Selection Criteria for Equipment
Part D-Planning the Movement of the ESSP
Loading Plan
Part E- Selecting the Site for Class III Supply Point and ESSP Operation
Figure 4-2. FSSP layout
Part F-Supervising the Movement of the ESSP
Bulk Reduction Storage Area
Part G- Environmental Considerations
Lesson 4 Practice Exercise - QM50990048
Lesson 5 Supervise the Operation of the FSSP
Part A-Supervising the Operation of the ESSP
Figure 5-1. Flow process chart for a 50,000-gallon collapsible tank
Product Consolidation and Circulation
Part B-Defense Plan
Protection of Petroleum Supplies
Part D-Preventive Maintenance Checks and Services(PMCS)
Lesson 5 Practice Exercise - QM50990057
Lesson 6 Direct Assault Hoseline Operations
Part A-The Assault Hoseline System
Figure 6-1. Laying the assault hoseline on a road
Part E-Maintaining Communications
Lesson 6 Practice Exercise - QM50990062
Terminal Learning Objective - QM50990063
Part A-Fare Components
Site Preparation
Figure 7-1. Typical FARE layout
Part D- Maintaining Communications
Part F- Safety
Air Traffic Control
Lesson 7 Practice Exercise - QM50990070
Lesson 8 Inland Petroleum Distribution System
Part A-Components
Figure 8-1. 19-foot aluminum pipe sections and 9.5-foot aluminum pipe nipples
Tactical Petroleum Terminal (TPT)
Figure 8-2. 800-GPM mainline pump
Part B- Quality Surveillance
Sample points
Part C-Pipeline Construction
Part D-Pump Station Operation
Part E - Site Selection and Planning
Part G-Communications
Lesson 8 Practice Exercise - QM50990082
Lesson 9 Compute BERM Requirements
Figure 9-1. Earthen firewall
Part B- Formula
Lesson 9 Practice Exercise
Lesson 10 Recommend Placement of Terminal Equipment and Manifolds
Part A-Types of Pipe and Couplings
Part B-Valves
Additional pipeline components
Part C-Fittings and Pipe Repair Accesories
Part E- Pipeline Scrapper Operations
Part F- Manifold Design Factors
Product Identification for Products
Lesson 10 Practice Exercise - QM50990095
Lesson 10 Practice Exercise -Cont.
Lesson 11 Direct Use of Pumps
Part A-Feet of Head and Pounds Per Square Inch
Part D-Pump Graphs
Pump graph application
800 GPM main line pump graph
Figure 11-2. 800 GPM main line pump graph
Lesson 11 Practice Exercise - QM50990103
Lesson 11 Practice Exercise -Cont.
Lesson 12 Pressure Testing Hose and Pipeline
Part A- Corrosion
Part B- Pipeline Testing
Compressed Air
Part C-Pipeline Patrolling
Foot and Motor Patrols
Lesson 12 Practice Exercise - QM50990111
Terminal Learning Objective - QM50990112
Part A Introduction
Part C-Slate Preparation
Requirements Footnote Card
Part E-Requirement Balances
Part F. Unforeseen Changes
Lesson 13 Practice Exercise - QM50990118
Lesson 14 Preparing Terminal Operating Reports
Part B-Format and Content
Part E-Miscellaneous Reports
Part G- Defense Energy Information System (DEIS)
Lesson 14 Practice Exercise - QM50990123
Lesson 15 Schedule and Evaluate Meter Verification
Part A - Types of Meters
Inferential Rate Meters
Part C-Proving Devices
Verification Records and Reports - QM50990128
Meter certification record
Lesson 15 Practice Exercise - QM50990130
Glossary - QM50990131
Glossary -Cont. - QM50990132
Glossary -Cont. - QM50990133
Answer Key and Feedback - QM50990134
Answer Key and Feedback - QM50990135
Answer Key and Feedback - QM50990136
Control Class III and Pipeline Operations